Kaifeng Xiangfu District2024Bid evaluation report on the construction project of supporting infrastructure for the renovation of old urban communities (inside and outside the red line) (Section 1)
一、Project description
Kaifeng Xingxiang Enterprise Management Consulting Co., Ltd. is commissioned by Jianxiang Industrial Co., LTD., Xiangfu District, Kaifeng City2024The construction project of supporting infrastructure for the renovation of old urban communities (inside and outside the red line) was open to tender2024年6月14Bid opening and evaluation activities were conducted in the Xiangfu District Public Resources Trading Center in accordance with the law。The bid evaluation committee has reviewed according to the requirements of the bidding documents, and confirmed by the tenderer, the bid evaluation results are now publicized as follows:
二、Project overview and bidding scope
2.1Project name: Xiangfu District, Kaifeng City2024The reconstruction of old urban areas (inside and outside the red line) supporting infrastructure construction projects
2.2Project Number:XXGK-2024-09
2.3Construction site: Xiangfu District, Kaifeng City
2.4Investment amount: approx1461万元
2.5Construction scale and content: two old residential renovation projects,They are: Xianfu Street area (supply and marketing society family home, Chaoyang community, old water works family home, teacher training school family home, etc.) and Yuanlou community;The backstreet alley project mainly includes the reconstruction of infrastructure such as Qingnian Road and Hongda Avenue on both sides and the road outside the red line of Yuanlou Community。
2.6Section division:
The project is divided into two bidding sections:
Section 1: Xiangfu District, Kaifeng City2024The reconstruction of old urban areas (inside and outside the red line) supporting infrastructure construction projectsEPCGeneral contract
Section 2: Xiangfu District, Kaifeng City2024Supervision of supporting infrastructure construction projects for the renovation of old urban communities (inside and outside the red line)
2.7Planned duration:
Section 1:180Calendar days (including design, procurement, construction and acceptance of important equipment and materials)。
Section 2: WithEPCGeneral contract period and defect liability period。
2.8Quality standard:
Paragraph 1: This project adopts EPCThe general contracting mode of the project includes the design of the construction drawings of the project, the budget of the construction drawings, the provision of relevant technical services during the construction period, etc., as well as the procurement of the main equipment and materials, construction and construction management until the completion and acceptance, and the defect repair and warranty work within the responsibility period of the project quality defect。
Section 2: Construction preparation stage, construction and installation stage (including defect liability period), equipment and materials procurement supervision services。
2.9Scope of tender:
Paragraph 1: This project adopts EPCThe general contracting mode of the project includes the design of the construction drawings of the project, the budget of the construction drawings, the provision of relevant technical services during the construction period, etc., as well as the procurement of the main equipment and materials, construction and construction management until the completion and acceptance, and the defect repair and warranty work within the responsibility period of the project quality defect。
Section 2: Design and construction preparation stage, construction and installation stage (including defect liability period), equipment and material procurement supervision services。
三、Number of members of the bid evaluation committee:7人:
1The leader of the judges: Su Liwei
2Other judges: Yang Dongrui,钱方,吕刚, 金戟, Jing Xinxin,Vanliuqiang
四、Bid evaluation situation
4.1Bidders who pass the bid evaluation stage after evaluation by the bid evaluation committee (in no particular order)
Section 1:
Bid the full name of the candidate |
Construction and installation rate(%) |
Design fee rate(%) |
Project leader |
Quality standard |
工期 |
Consortium leader: Henan Xiangying Municipal Engineering Co., LTD.; Consortium member: Anyang Municipal Design and Research Institute Co., LTD |
99.26 |
1.80 |
Project Manager:Liu Xulong Name of technical leader:Lun Guoxuan Head of Design:Lu Xiaonan |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: Henan Provincial City Control Construction Group Co., LTD. Consortium member: Zhejiang Xinshang Engineering Design Co., LTD |
99.70 |
1.78 |
Project Manager: Yao Hui Name of technical leader: Qi Yanyong Design Director: Han Zhiqiang |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: Shihua 99 Construction Engineering Group Co., LTD.; Consortium member: Zhongyi Engineering Design Co., LTD |
99.60 |
1.75 |
Project Manager: Zhu Hongbin Name of technical person in charge: Wang Liubiao Design Leader: Mu Kangzheng |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: China Construction Fangda Construction Engineering Co., LTD.; Consortium member: Sanmenxia City Planning, Survey and Design Institute |
99.35 |
1.80 |
Project Manager: Yuan Yongjun Technical person in charge name: Li Haolei Design Leader: Yang Qiyong |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: Henan Lianchuang Construction Engineering Co., LTD.; Consortium member: Mingyang Engineering Design Group Co., LTD |
99.53 |
1.77 |
Project Manager: Fan 强 Technical leader name: Ma Jidong Design Director: Duan Jingyang
|
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: Henan Kaizhixing Construction Engineering Co., LTD. Consortium member: Zhongzi Design Group Co., LTD |
99.00 |
1.79 |
Project Manager: Hou Yuhong Name of technical leader: Zheng Dongjun Design leader: Chen Shiying |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: Henan Minggui Construction Engineering Co., LTD. Consortium member: Kaifeng Municipal Engineering Design & Research Co., LTD |
98.82 |
1.80 |
Project Manager: Pan Fengxia Name of technical leader: Fan Qianjin Design Leader: Tan Huang |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: Kaifeng Xiangfu Municipal Engineering Co., LTD.; Consortium member: Xuzhou Municipal Design Institute Co., LTD |
98.76 |
1.80 |
Project Manager: Yaqiong Wang Name of technical leader: Wang Shuzheng Design Director: Wu Lijuan |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: Henan Zhongli Construction Engineering Co., LTD.; Consortium member: Dalian Municipal Design and Research Institute Co., LTD |
98.69 |
1.80 |
Project Manager: Yan Hongjun Name of technical leader: Zhang Qiqi Design Leader: Sun Bo |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: Henan Zhongying Construction Co., LTD.; Consortium member: Lixin Engineering Design Co., LTD |
96.43 |
1.75 |
Project Manager: Yongbo Zhao Name of technical leader: Wang Yufeng Design leader: Liang Yonglin |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: Henan Yiguang Construction Engineering Co., LTD.; Consortium member: Zhongzhi Design Group Co., LTD |
99.23 |
1.78 |
Project Manager: Yin Yunhui Name of technical leader: Cao Zhipeng Design leader: Huang Fu Xiaomei |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: Henan Anjun Municipal Garden Engineering Co., LTD.; Consortium member: Guangzhou Kecheng Architectural Design Co., LTD |
98.98 |
1.79 |
Project Manager: Naga Takone Name of technical leader: Wang Shiyou Design Director: Zeng Rong |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: Henan Hongfa Municipal Engineering Co., LTD.; Consortium member: Henan Urban and Rural Architectural Design Institute Co., LTD |
98.89 |
1.79 |
Project Manager: Niu Deqing Name of technical leader: Li Huiyi Design leader: Shen Qinhong |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Consortium leader: Henan Qianzhuo Construction Engineering Co., LTD.; Consortium member: Zhumadian Architectural Survey and Design Institute Co., LTD |
99.16 |
1.80 |
Project Manager: Jiang Panpan Name of technical leader: Zhu Shuyuan Design leader: Qiu Yunhui |
This project adopts EPC The general contract mode of the project, including the construction drawing design of the project, the construction drawing budget, during the construction period Provide related technical services, as well as major equipment and materials procurement, construction and construction management until completion acceptance, project quality Defect repair and warranty work within the defect liability period |
180 Calendar days (including design, procurement, construction and acceptance of important equipment and materials) |
Section 1: Bid evaluation methods according to the bidding documents 2.1.5 If the bidder's offer appears in parallel, it will be shortlisted for the bidding candidates at the same time, and the recommended list is as follows:
4.2Evaluation of candidate project managers
定标Full name of candidate |
Personnel category |
姓名 |
Practice qualification certificate or title certificate name |
Certificate number |
Consortium leader: Henan Zhongying Construction Co., LTD.; Consortium member: Lixin Engineering Design Co., LTD |
Project manager |
Zhao Yongbo |
Class II Construction Engineer registration Certificate
|
豫 241212287130 |
Technical director |
Wang Yufeng |
Certificate of professional title |
C19033130901147 |
|
Design leader |
Liang Yonglin |
Primary registration Architect certificate |
20114401782 |
|
Consortium leader: Henan Zhongli Construction Engineering Co., LTD.; Consortium member: Dalian Municipal Design and Research Institute Co., LTD |
Project manager |
Yan Hongjun |
注册 Builder's certificate |
豫2411415813909 |
Technical director |
Zhang Qiqi |
Certificate of professional title |
C201909A7 990000000079 |
|
Design leader |
孙博 |
Certificate of registered architect |
20212101625 |
|
Consortium leader: Kaifeng Xiangfu Municipal Engineering Co., LTD.; Consortium member: Xuzhou Municipal Design Institute Co., LTD |
Project manager |
Wang Yaqiong |
Certificate of Registration of Class II Constructor |
豫 241151577406 |
Technical director |
Wang Shuzheng |
Certificate of professional title |
C05006180900097 |
|
Design leader |
Wu Lijuan |
Grade I Registered architect Certificate |
20203202907
|
|
Consortium leader: Henan Minggui Construction Engineering Co., LTD. Consortium member: Kaifeng Municipal Engineering Design & Research Co., LTD |
Project manager |
Pan Fengxia |
Class I Constructor Registration Certificate |
豫 1412017201833172 |
Technical director |
Fan Qian Qian |
Certificate of professional title |
C20190974169900001479 |
|
Design leader |
黄坦 |
Grade I Registered architect Certificate |
20083101747 |
|
Consortium leader: Henan Hongfa Municipal Engineering Co., LTD.; Consortium member: Henan Urban and Rural Architectural Design Institute Co., LTD |
Project manager |
nitrachine |
Builder's registration certificate |
241171723747 |
Technical director |
Li Huiyi |
Certificate of professional title |
C19033009180900132 |
|
Design leader |
Shen Qinhong |
Grade I Registered architect Certificate |
20184101016 |
|
Consortium leader: Henan Anjun Municipal Garden Engineering Co., LTD.; Consortium member: Guangzhou Kecheng Architectural Design Co., LTD |
Project manager |
Aga Takane |
Class I Constructor Registration Certificate |
241141568554 |
Technical director |
The prince has a |
Certificate of professional title |
C09902170900 291 |
|
Design leader |
曾嵘 |
Grade I Registered architect Certificate |
20194402482 |
|
Consortium leader: Henan Kaizhixing Construction Engineering Co., LTD. Consortium member: Zhongzi Design Group Co., LTD |
Project manager |
Hou Yuhong |
Class I Constructor Registration Certificate |
241111121855 |
Technical director |
Zheng Dongjun |
Certificate of professional title |
C201909741699 00001484 |
|
Design leader |
Chen Shiying |
Grade I Registered architect Certificate |
20235200583 |
|
Consortium leader: Henan Qianzhuo Construction Engineering Co., LTD.; Consortium member: Zhumadian Architectural Survey and Design Institute Co., LTD |
Project manager |
Jiang Panpan |
Builder's registration certificate |
豫 241151577314 |
Technical director |
Zhu Shuyuan |
Certificate of professional title |
C2019094002210 0000357 |
|
Design leader |
Qiu Yunhui |
Certificate of registered architect |
20104100669 |
|
Consortium leader: Henan Yiguang Construction Engineering Co., LTD.; Consortium member: Zhongzhi Design Group Co., LTD |
Project manager |
Yin Yunhui |
Builder's registration certificate |
豫 241141560721 |
Technical director |
Cao Zhipeng |
Certificate of professional title |
C202309C9022500 000288 |
|
Design leader |
Hwang Pu Xiaomei |
Grade I Registered architect Certificate |
20134100848 |
4.3Evaluation candidate performance:/
4.4The qualifications and ability of the successful candidate to respond to the requirements of the bidding documents
4.4.1Qualifications required by the bidding documents
Bidder qualification requirements |
3.1.1Qualification: The bidder must have a valid business license。The bidder shall have the qualification of Grade 3 (including Grade 3) or above for general contracting of construction engineering and Grade 3 (including Grade 3) or above for general contracting of municipal public engineering approved by the competent construction administrative department;The bidder shall have Grade B (including Grade B) or above of engineering design and construction industry (construction engineering) and Grade B (including Grade B) or above of municipal industry (road engineering and drainage engineering) issued by the construction administrative department;Have valid safety production license。 3.1.2Project leader requirements: (1Project Manager: The project manager to be assigned by the bidder shall have the qualification of registered construction engineer of Grade II (including Grade II) and Municipal Public engineering professional Grade II (including Grade II) or above,And have effective safety production assessment certificate,And did not serve as the construction project manager of other construction projects under construction (provide construction project manager without construction commitment),Must be the leader of the staff of the unit,Provide the labor contract and the unit 2023 年 10月 1 Pay continuously since today6Proof of social security for a month (insufficient new employees) 6 Months from the date of appointment)。 (2Technical person in charge: The proposed technical person in charge shall have the intermediate or above technical title of the relevant professional, and provide the labor contract and the unit 2023 年 10月 1 Pay continuously since today6Proof of social security for a month (insufficient new employees) 6 Months from the date of appointment)。 (3Project design leader: must have two (including two) or above registered architect qualification and intermediate or above technical title。Provide the labor contract and the unit 2023 年10月 1 Since the continuous payment of nearly 6 Proof of social security for a month (insufficient new employees) 6 Months from the date of appointment)。 3.1.3Consortium bids are accepted for the first section of the project, provided that the number of members in the consortium shall not exceed3家。If a consortium bids, the following requirements shall also be met: (1If a consortium participates, it shall submit the consortium agreement and indicate the work and responsibilities to be undertaken by the leader and the parties, and promise that the parties to the consortium will bear joint and several liabilities to the tenderer once the contract is concluded; (2If members of a consortium with similar qualifications undertake the same work according to the division of labor of the consortium, the qualification level shall be determined according to the lower qualification level of the consortium members; (3Where a consortium participates in the bidding activities, the parties to the consortium may not participate in the bidding activities under the same contract separately or form a consortium with other consortium members; (4The consortium leader must be the construction party。The legal representative of the lead or its authorized entrusted agent is responsible for signing the relevant documents of this bidding activity. If it is necessary to seal, the lead shall seal it。 (5In the form of a consortium to participate in the bidding activities, the leader must be in the Kaifeng public resources electronic trading service platform member system CA Digital Certificate Download tender documents and upload tender documents, which are not required for consortium members。 3.1.4Financial requirements: Provided2020、2021、2022 The annual financial report audited by an accounting firm shall be counted from the time of establishment of a newly established company if it is less than three years old。 3.1.5Performance requirements: enterprise self2021年1月1Have undertaken one similar project performance since the date of signing the contract (subject to the date of signing the contract), (subject to the date of signing the contract, the notice of winning the bid and the contract shall be provided)。 3.1.6Reputation requirements: Yes2020年1月1Bidders included in the list of persons subject to enforcement for dishonesty, parties to major tax violation cases, and records of serious illegal and dishonest acts of government procurement after the date refuse to participate in the project bidding;Bidders may submit their bids through the "Credit China" website (www.creditchina.gov.cn), China Government Procurement Website (www.ccgp.gov.cnChannel to inquire the bidder's credit record, and provide the inquiry website (the inquiry date is after the announcement date, if the consortium bid, the consortium members need to provide)。 3.3Financial requirements: The bidder must provide documents issued by an accounting firm or audit institution2023Annual financial audit report (provided by newly established enterprises according to the actual year of establishment)。 3.4Reputation requirements: The bidder will be refused to participate in the project bidding activities if there are administrative penalties, litigation or arbitration cases, executed information, etc. : ①.Bidding enterprises or individuals are listed in the "blacklist" of construction market players and within the management period, the inquiry channel National construction market supervision public service platform (http://jzsc.mohurd.gov.cn/home), need to provide online query screenshot, query objects include legal person, legal representative, project director;2..National Enterprise Credit Information Publicity system (http://www.gsxt.gov.cn/If the list of serious violations of law and dishonesty is within the management period, it is necessary to provide online query screenshots, and the query object is a legal person;3..On the "Credit China" website (http://www.creditchina.gov.cn/The "seriously untrustworthy subjects" in the list of serious untrustworthy subjects in the key areas of "credit services" are restricted or prohibited from participating in tendering and bidding activities and are within the management period,A screenshot of the query is required,The query object is a legal person,The contents of the inquiry are: the person subject to enforcement of dishonesty, the record list of serious illegal and dishonest behaviors of government procurement, the main body of major tax law and dishonesty, the list of serious untrustworthy enterprises, and the list of serious untrustworthy subjects of safety production,The query object is a legal person。Provide screenshots of web queries and stamp them with official seal。After inquiry, those who have the above serious illegal and dishonest acts will be disqualified from bidding; |
4.4.2Determine the qualifications and abilities of the candidates to respond to the requirements of the bidding documents
定标Full name of candidate |
Response condition |
|
Henan Zhongying construction Co., LTD |
responded |
|
Henan Zhongli Construction Engineering Co., LTD |
responded |
|
Kaifeng Xiangfu Municipal Engineering Co., LTD |
responded |
|
Henan Minggui construction engineering Co., LTD |
responded |
|
Henan Hongfa Municipal Engineering Co., LTD |
responded |
|
Henan Anjun Municipal garden engineering Co., LTD |
responded |
|
Henan Kai Star construction engineering Co., LTD |
responded |
|
Henan Qianzhuo construction engineering Co., LTD |
responded |
|
Henan Yiguang construction Engineering Co., LTD
|
responded |
|
4.5Circumstances and reasons for rejecting the bid:Section 1:List and reasons for failure: Zhongke Xinhe Construction Development Co., LTD., Henan Yukun Construction Engineering Co., LTD., Henan Hengyue Construction Engineering Co., LTD., Henan Qichuan Construction Engineering Co., LTD., Zhongcheng Yongfeng Construction Group Co., LTD5The company fails to provide the financial audit report as required by the bidding documents;Henan Muting Construction Engineering Co., Ltd. did not provide the credit inquiry certificate of the consortium members according to the requirements of the bidding documents;Henan Regular Construction Engineering Co., Ltd. has not made service commitments according to the requirements of the bidding documents。以上7If the bidder fails to pass the detailed evaluation, it shall be treated as invalid bid。
无
According to the BianPublic Administration Office (2020)13The document stipulates that if the bidder has objections to the above results, it can raise objections to the tenderer on the public resources trading information network cable in Kaifeng City during the publicity period, and the overdue will no longer be accepted, and the tenderer should be from the date of receipt of the objection3Reply within days,If the objector still has objections to the reply or the tenderer fails to make a reply within the prescribed time, the objector may do so on the date of publicity10Within days (objection reply period does not count) in the Kaifeng public resources trading information network online complaint。(In the important document column of the Kaifeng public resources trading information website, there are text formats and requirements for objections and complaints of construction projects)。
Tenderer: Kaifeng Xiangfu District Jianxiang Industrial Co., LTD
Address: Kaifeng City Xiangfu District youth Avenue455号
Contact: Mr. Gao
Contact number:18738966589
Bidding Agency: Kaifeng Xingxiang Enterprise Management Consulting Co., LTD
联 系 Person: Mr. Liang
电 话:27886591
地 Address: 10th floor, Xiangfu District Citizens Home
Project contact: Mr. Liang
电 话:27886591
The bidding announcement is also published on the website of "China Tendering and Bidding Public Service Platform", "Henan Electronic Tendering and Bidding Public Service Platform" and "Kaifeng Public Resources Trading Information Network"。
All rights reserved:Kaifeng city public resources trading information networkHost: Kaifeng public resources trading information network